Construction & Contracting

Building without a permit: what happens to your construction contract?

Vianto Pashku - Lawyer · · 7 min
Table of contents

In short

A construction contract that has not been performed in accordance with the planning permit is not automatically void. Recent case law carefully distinguishes between what affects the contract itself, what the architect should have done under his duty to inform, and who ultimately pays for the demolition — a division that often turns out expensive for those who look the other way.

You built or renovated, and it later turns out that the works were not covered by a valid planning permit. The permit had expired, had been annulled, or the execution deviated from it. An unpleasant finding. An even more unpleasant question: can you still hold your contractor or architect liable under the contract, or is everything that was agreed legally non-existent? Belgian case law offers a nuanced answer — with major practical consequences.

Many building owners face a double shock at that moment: an administrative sanction (restoration, regularisation or demolition) and a private-law file in which the question of fault suddenly becomes crucial. Who knew what? Who should have warned? And how far does the liability extend of the architect who drew up the plans or the contractor who carried them out? In this article you will read how the Courts of Appeal of Brussels and Antwerp have recently answered these questions, and what steps you can take yourself to protect your position.

No automatic nullity

The basic principle: a construction or architect's contract is not automatically void when the works have been carried out without or contrary to a permit. The Court of Appeal of Brussels ruled on 25 January 2024 (Brussels 2nd ch. F, JLMB 2024, issue 42, 1903) on a case in which houses had been built after the planning permit had lapsed or contrary to the permit issued. The court rejected the argument of automatic nullity and set out the following principle: the contracts are not void if the illegality committed dates from after the conclusion of the contract and is unrelated to its subject matter.

The reasoning: the architect's contract itself had a lawful subject — the drawing up of plans and/or supervision of the works. That the performance subsequently became unlawful does not affect the validity of the contract itself, unless the parties intended to circumvent the statutory architectural supervision obligation. A person in an unlawful situation who claims damages is not necessarily pursuing the protection of an unlawful interest. The interest in bringing an action is only unlawful when the claim seeks to maintain an unlawful situation.

For you as building owner, this means: even in the event of permit problems, you can still hold your contractor or architect liable in contract for non-performance, defective performance or breach of the duty to inform. The permit issue plays out on a different legal level.

The architect and the demolition: a heavy responsibility

Another case shows how far-reaching the liability can be. The Court of Appeal of Antwerp ruled on 6 June 2023 (Antwerp B2E2nd ch. no. 2022/AR/272, Limb.Rechtsl. 2023, issue 4, 327) on a building project that had initially started under a valid permit, but the permit was later annulled. The building had to be demolished — a hefty cost.

The architect was held liable on the basis of a breach of his pre-contractual duty to inform (articles V.2 and VI.64 of the Code of Economic Law). He had insufficiently informed the building owner about the main characteristics of his service — including which tasks were his, what the relationship was between his tasks and those of the contractor, and how site supervision was arranged. Because of this failure, there was no clarity as to who had to warn the building owner and when.

The court ruled that the failure to comply with the duty to inform constituted fault within the meaning of article 1382 of the old Civil Code, in causal connection with the damage — namely the demolition cost. The reasoning: had the architect complied with his duty to inform, he would have been more involved from the outset, he would have warned about the risk of starting the works before the expiry of the appeal period, and the damage would not have occurred or would have been less.

For the building owner, this is an important ruling: an architect who fails in his duty to inform about his own tasks can be held liable for the demolition cost — even though the direct cause of the demolition lies in the annulment of a permit over which he had no control.

The limits: expert investigation and subsidiarity

Not every permit problem automatically leads to a successful claim. The Court of First Instance of Brussels (Brussels Dutch-speaking Court no. 2021/1294/1, 26 July 2021, T.App. 2023, issue 3, 23) ruled on a building owner who had had a duplex apartment converted into a triplex. Instead of a staircase, he chose a lift. Afterwards, the fire brigade indicated that the installation was not in accordance with the environmental permit. The building owner summoned the developer, the architect and the installer and requested the appointment of a court expert.

The court dismissed the application on the basis of the principle of subsidiarity: the applicant did not provide any prima facie evidence of his claim. A court expert is not intended to make up for a failing burden of proof. The building owner could therefore not try to obtain information "via" an expert that he should have gathered himself first.

The practical lesson: a claim for permit problems requires a minimum of your own documentation — site correspondence, e-mails with the architect about the planning situation, photos, findings by the authorities, fire brigade advice — before you may ask a court to appoint an expert. A mere suspicion of irregularity is not sufficient.

Mistake and fraud as alternatives

In addition to the duty to inform and non-performance, Belgian law offers two further angles for permit problems: mistake (article 5.33 Civil Code) and fraud (article 5.36 Civil Code). Where the contractor or architect deliberately gave you incorrect information about the validity of the permit, or where you were essentially mistaken about the lawfulness of the project, this may lead to nullity of the contract with restitution of what has already been performed.

Article 5.33 of the Civil Code requires the mistake to concern an element of the contract that was decisive for the party and that the other party was or should have been aware of. In the case of architects and contractors, who are professionals in the field of planning law, this "should have known" test is set relatively low.

For the difference between contractual liability and the action for annulment, and for the broader context of your rights, see the pillar on rights and obligations of the building owner in construction contracts.

And what if the permit did exist, but the contractor deviated from it?

Another situation: the permit is valid, but the contractor deviates from what it states. A storey height that does not match, a window in a different location, an extension that has not been permitted. In this scenario, the construction contract itself is not at issue — the contractor is breaching his contractual obligation to carry out the works in accordance with the plans and the permit.

The contractor's duty to warn arises here in a twofold manner: he must warn the building owner when he sees that an execution choice deviates from the permit, and he must himself refuse to work contrary to the permit without an express written instruction. For more on the duty to warn, see the spoke on the contractor who failed to warn.

What do you do in practice?

Where you are faced with a permit problem that threatens to lead to restoration, regularisation or demolition, some basic principles apply.

Gather your file: all correspondence with contractor and architect, the permit file, the opinions of advisory bodies, the site meeting minutes, the official notifications from the authorities. Request an independent assessment: a second architect or a lawyer can assess the legal position of your contractor and architect on the basis of their duty to inform and their supervisory duty. Instruct a lawyer in good time: claims for breach of the duty to inform or non-performance are time-barred within ten years of the fault (article 2262bis Civil Code), but claims for annulment of the contract may be subject to shorter periods. Investigate all liability insurance policies: both architect and contractor have compulsory professional liability insurance, and this insurance can in most cases be addressed directly — even in the event of bankruptcy of the architect or contractor.

Reius Advocaten assists individuals and businesses in permit disputes combined with construction files. The combination of administrative law (permit) and private law (construction) requires an integrated approach. Contact us at info@reius.be for an initial assessment of your file.

Frequently asked questions

Is my construction contract automatically void if the permit falls away?

No. The Court of Appeal of Brussels confirmed on 25 January 2024 (JLMB 2024, issue 42, 1903) that a construction or architect's contract is not automatically void if the performance subsequently proves unlawful. Nullity only applies where, at the time of conclusion of the contract, the parties explicitly intended to circumvent the law. In other cases, the contract remains valid and you can enforce your contractual rights.

Who pays for the demolition if the permit is annulled?

That depends on the chain of causation. The Court of Appeal of Antwerp ruled on 6 June 2023 (Limb.Rechtsl. 2023, issue 4, 327) that an architect who fails in his pre-contractual duty to inform (articles V.2 and VI.64 of the Code of Economic Law) may share liability for the demolition cost — even where the direct cause of the demolition lies in an administrative annulment. The causal link runs via the reasoning that "had the architect informed correctly, execution would have been postponed or would have proceeded differently". For the building owner, this is an important avenue of recovery.

Can I have a court expert appointed to prove fault?

Not without prima facie evidence of your own. The Court of First Instance of Brussels ruled on 26 July 2021 (T.App. 2023, issue 3, 23) that a court expert is not intended to make up for a failing burden of proof. You must first submit documentation yourself — site correspondence, photos, e-mails, official decisions — before the court will allow an expert investigation on the basis of article 19, paragraph 3 of the Judicial Code.

Does it make a difference whether I am an individual or a company?

Yes, and on several levels. As an individual consumer, you enjoy the protection of Book VI of the Code of Economic Law (duty to inform, transparency requirement, right of withdrawal in certain contexts). As a business, the B2B regime of articles VI.91/3 to VI.91/5 of the Code of Economic Law has applied since 1 December 2020. For details on the latter, see the spoke on unfair terms in B2B construction contracts. The liability rules themselves (duty to warn, ten-year liability) are the same for individuals and businesses.

What if the architect says he did not know the permit was invalid?

An architect is an expert in planning law. The duty to inform under article 5.16 of the Civil Code requires him to inform you about everything that may materially influence the execution — including the validity of the permit, the expiry of administrative appeal periods, and the risk associated with an early start. An architect who ignores or fails to communicate these risks breaches his duty to inform. Whether this also leads to liability for the demolition cost depends on the causal link — but the Antwerp case law of 6 June 2023 has significantly lowered the threshold in that regard.

Can I regularise my works instead of demolishing them?

Often yes, and that is usually the first avenue you will examine. A regularisation permit is a new permit application for works already carried out. It is assessed on the same grounds as an ordinary application — compatibility with the regional plan, sound spatial planning, the opinion of the bodies concerned. If restoration proceedings are pending before the criminal court, a valid regularisation may render the demolition unnecessary (article 6.2.1 et seq. Flemish Code on Spatial Planning; article 192 et seq. Brussels Spatial Planning Code; article D.IV.99 et seq. Walloon Code). The financial impact remains limited, since you only pay the regularisation levy and possibly a betterment charge. In the event of a successful regularisation, your claim against the contractor or architect may be limited to the additional costs and not the full demolition cost.

Do I have anything to fear in criminal law as building owner?

Possibly. Planning offences are punishable in the three regions, and the building owner as principal can be prosecuted — alongside the contractor and the architect who carried out the works. The criminal consequences vary: fines, restoration orders, and in serious cases a prison sentence. Pleading that you acted in good faith and relied on your architect's advice may play a role in sentencing — but it does not automatically relieve you of liability. It is therefore crucial, as soon as a permit problem is identified, to instruct a lawyer who handles both the civil and criminal tracks.

Will my legal expenses insurance cover a permit dispute?

Often only partially. Classic legal expenses insurance policies usually cover civil disputes (your claim against contractor or architect), but often exclude or limit cover for administrative proceedings before the Council for Permit Disputes, the Council of State or the criminal court. Read your policy conditions carefully: the "exclusions" and "waiting periods" are decisive. Additional legal expenses cover for planning law or a specific ABR policy (All Construction Site Risks) may then offer a solution — although you must take it out before the problems arise.